Laying floor screed

- 14.12.2020

1611916711863.jpg

Laying wall plasters

- 16.10.2020

1605296324198_edited.jpg

Installation of gas and heating installation 

- 10.11.2020

1605296324271_edited.jpg

Laying roof waterproofing membrane "Sika"

- 28.11.2020

1611916711781.jpg

Enlargement - 1996

G0037549-1 copy.png

Demolition - 24.10.2019

20191024_182201.jpeg

Construction of a retaining wall - 24.10.2019

Screenshot 2019-12-23 at 14.01.34.png

Excavation - 30.11.2019

IMG_3527.JPG

Foundation - 06.12.2019

Screenshot 2019-12-23 at 16.35.42.png

Construction of floor -1 -30.11.2019

IMG_4385.HEIC

Construction of floor 0 

- 16.01.2020

IMG_20200129_155430 copy.jpg

Construction of floor +1

- 25.02.2020

IMG_20200228_094944_edited.jpg

Construction of floor +2

- 15.03.2020

IMG_20200320_122747.jpg

Construction of floor +3 

- 05.04.2020

IMG_20200407_195614.jpg

Construction of floor +4 

- 29.04.2020

IMG_20200424_162230.jpg

Construction of rooftop 

- 17.05.2020

IMG_20200514_143011.jpg

Finishing structural work

- 10.06.2020

1600355000129.jpg

Installation of water pipes and electrical wires

- 15.07.2020

1600355811519_edited.jpg

Window installation

- 19.08.2020

1600356092676_edited.jpg

First House - 1959